Sundon Pivoted Power
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Solar
- Total capacity
- 49.9 MW
- Connected now
- 49.9 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001123
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerTechnology changed from Storage to Solar
- 29 Oct 2024 register49.9 MW now connected
- 29 Oct 2024 registerStatus changed from Awaiting Consents to Built
- 28 Jul 2023 registerConnection point changed from Sundon GSP to Sundon 400kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Sundon to Sundon GSP)
- 31 Aug 2021 registerConnection date moved from 31 Oct 2022 to 31 Oct 2023 (+12 months)
Also at Sundon 400kV Substation
Substation view3 other projects, 1.2 GW still to connect at this substation in total.