Kirkby (Tertiary)
- Connection date
- 30 Aug 2027
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001083
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 10 Apr 2026 registerConnection point changed from Kirkby GSP (ENW) to Kirkby 275/33kV Substation
- 24 Dec 2024 registerConnection date moved from 31 Oct 2025 to 30 Aug 2027 (+22 months)
- 26 Nov 2024 registerConnection point changed from Kirkby 275kV Substation to Kirkby GSP (ENW)
- 26 Nov 2024 registerTechnology changed from Storage to Storage, Solar
- 28 Jul 2023 registerCapacity changed from 49.9 MW to 57 MW
- 28 Jul 2023 registerConnection date moved from 1 Nov 2022 to 31 Oct 2025 (+36 months)
- 29 Jul 2022 registerSubstation name updated in the register (from Kirkby 275kV to Kirkby 275kV Substation)
- 26 Feb 2021 registerConnection date moved from 11 Jan 2022 to 1 Nov 2022 (+10 months)
Also at Kirkby 275/33kV Substation
Substation view1 other project, 114 MW still to connect at this substation in total.