Carrington
- Connection date
- 31 Oct 2028
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001025
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Dec 2025 registerMarked as Gate 1
- 26 Nov 2024 registerTechnology changed from Storage, Solar to Storage
- 28 Jun 2024 registerTechnology changed from Storage to Storage, Solar
- 28 Nov 2023 registerCapacity changed from 49.9 MW to 57 MW
- 28 Nov 2023 registerConnection date moved from 31 Oct 2022 to 31 Oct 2028 (+72 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Carrington 275kV to Carrington 275kV Substation)
Also at Carrington 275kV Substation
Substation viewNo other projects in the register at this connection point.