Bustleholme
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 1 Feb 2021
Sandwell, reference DC/20/64437 · Source: REPD - Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 57 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001039
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Jun 2024 register7.1 MW now connected
- 28 Jun 2024 registerCapacity changed from 49.9 MW to 57 MW
- 30 Jun 2023 register49.9 MW now connected
- 30 Jun 2023 registerStatus changed from Scoping to Built
- 23 Dec 2022 registerSubstation name updated in the register (from Bustleholm to Bustleholm GSP)
- 31 May 2022 registerConnection date moved from 22 Oct 2021 to 31 May 2022 (+7 months)
Also at Bustleholm GSP
Substation viewNo other projects in the register at this connection point.