- Connection date
- 18 Dec 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001077
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection point changed from Norwich GSP to Norwich Main 400kV Substation
- 27 Jun 2025 registerConnection date moved from 31 Oct 2024 to 18 Dec 2025 (+14 months)
- 30 Jun 2023 registerConnection point changed from Mablethorpe 400kV to Norwich GSP
- 30 Jun 2023 registerCapacity changed from 49.9 MW to 57 MW
- 30 Jun 2023 registerTechnology changed from Storage to Storage, Solar
- 29 Jul 2022 registerConnection point changed from Norwich Main 400kV to Mablethorpe 400kV
Also at Norwich Main 400kV Substation
Substation view3 other projects, 4.4 GW still to connect at this substation in total.