Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Exeter (Tertiary)

PIVOTED POWER LLP at Exeter 400kV Substation

Connection date
16 Jun 2028
Gate
Not stated
Status
Awaiting Consents
Technology
Storage + Solar
Total capacity
57 MW
Connected now
0 MW
Still to connect
57 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001047
In the register since
January 2021 or earlier

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1049.949.916 Jun 2028Not statedAwaiting Consents
207.1576 Dec 2036Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 28 Mar 2025 register
    Stage 1: Connection date moved from 6 Dec 2036 to 16 Jun 2028 (−102 months)
  • 28 Mar 2025 register
    Stage 1: Status changed from Scoping to Awaiting Consents
  • 28 Mar 2025 register
    Stage 2: Capacity changed from 57 MW to 7.1 MW
  • 28 Mar 2025 register
    Stage removed (49.9 MW from 1 Nov 2025)
  • 31 Jan 2025 register
    Technology changed from Storage to Storage, Solar
  • 31 Jan 2025 register
    New stage added (49.9 MW from 6 Dec 2036)
  • 31 Jan 2025 register
    New stage added (57 MW from 6 Dec 2036)
  • 23 Dec 2022 register
    Connection point changed from Exeter Main 400kV to Exeter 400kV Substation
  • 26 Feb 2021 register
    Connection date moved from 11 Jan 2025 to 1 Nov 2025 (+10 months)

Also at Exeter 400kV Substation

Substation view

3 other projects, 1.2 GW still to connect at this substation in total. 347 MW is due to connect here before this project’s connection date of 16 Jun 2028.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO