Willington
- Connection date
- 30 Jun 2026
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000326
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Dec 2025 registerMarked as Gate 1
- 28 Apr 2023 registerCapacity changed from 49.9 MW to 57 MW
- 28 Apr 2023 registerConnection date moved from 31 Oct 2022 to 30 Jun 2026 (+44 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
Also at Willington East 400kV Substation
Substation view3 other projects, 402 MW still to connect at this substation in total.
- Willington East 1 (Tertiary)ENSO GREEN HOLDINGS U LIMITED, Storage with solar or wind, Gate 1Oct 202747.5 MW
- Willington East 2 (Tertiary)ENSO GREEN HOLDINGS SS LIMITED, Storage with solar or wind, Gate 1Jul 202847.5 MW
- Willington PV & BESSWILLINGTON ENERGY PARK LIMITED, Storage with solar or wind, Gate 1Oct 2033250 MW