Projects / England and Wales
Connection date
1 Nov 2023
Gate
Gate 1
Status
Awaiting consent
Technology
Storage
Total capacity
49.9 MW
Connected now
0 MW
Still to connect
49.9 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001068
Tracked since
14 Aug 2026

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at SEABANK 400/33kV SUBSTATION

Substation view

No other projects in the register at this connection point.