Seabank (Tertiary)
- Connection date
- 1 Nov 2023
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001068
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Mar 2026 registerConnection point changed from Seabank 400kV Substation to SEABANK 400/33kV SUBSTATION
- 24 Mar 2026 registerMarked as Gate 1
- 23 Dec 2022 registerSubstation name updated in the register (from Seabank 400kV to Seabank 400kV Substation)
- 26 Feb 2021 registerConnection date moved from 11 Jan 2023 to 1 Nov 2023 (+10 months)
Also at SEABANK 400/33kV SUBSTATION
Substation viewNo other projects in the register at this connection point.