Transmission / Projects / England and Wales
West Weybridge
- Connection date
- Left 28 Jun 2024
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001108
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 28 Jun 2024 registerLeft the register (49.9 MW from 31 Oct 2027)
- 23 Dec 2022 registerSubstation name updated in the register (from West Weybridge 275kV to West Weybridge 275kV Substation)
- 25 Feb 2022 registerConnection date moved from 31 Oct 2023 to 31 Oct 2027 (+48 months)
Also at West Weybridge 275kV Substation
Substation view2 other projects, 114 MW still to connect at this substation in total.