Kemsley 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Ouse Energy Storage | Ouse Energy Limited | Storage | 249 | 27 Oct 2027 | Not stated | Scoping |
| Kemsley | PIVOTED POWER LLP | Storage | 0 | Connected | Not stated | Built |
Left the register since January 2021: Ridham Battery Storage (350 MW).
Recent changes
- Ouse Energy StorageEngland and Wales, StorageConnection date moved from 24 Aug 2026 to 27 Oct 2027 (+14 months)+14 mo
- Ridham Battery StorageEngland and Wales, StorageLeft the register (350 MW from 31 Oct 2031)350 MW
- KemsleyEngland and Wales, StorageConnection point changed from Kemsley 400/132kV Substation to Kemsley 400kV Substation
- Ouse Energy StorageEngland and Wales, StorageConnection point changed from Kemsley 400/132kV Substation to Kemsley 400kV Substation
- Ridham Battery StorageEngland and Wales, StorageConnection point changed from Kemsley 400/132kV Substation to Kemsley 400kV Substation
- Ridham Battery StorageEngland and Wales, StorageAdded to the registerNew
- Ouse Energy StorageEngland and Wales, StorageAdded to the registerNew
- KemsleyEngland and Wales, StorageConnection date removed (was 18 Jan 2021)
- KemsleyEngland and Wales, StorageConnection date set to 18 Jan 2021
- KemsleyEngland and Wales, Storage49.9 MW now connectedConnected
- KemsleyEngland and Wales, StorageStatus changed from Awaiting Consents to Built
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?