Projects / England and Wales
- Connection date
- 31 Oct 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001136
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 31 Oct 2029 | Gate 1 | Scoping |
| 2 | 0 | 50.1 | 100 | 31 Oct 2036 | Gate 1 | Scoping |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Alverdiscott 400kV Substation
Substation view13 other projects, 12.3 GW still to connect at this substation in total.
- Merlin Offshore Wind FarmOFFSHORE WIND LIMITED, Offshore wind, Gate 1Nov 2028300 MW
- Petroc Offshore Wind FarmBLUEFLOAT ENERGY UK HOLDINGS LIMITED, Offshore wind, Gate 1Mar 2029300 MW
- Gwynt Glas Offshore Wind FarmGWYNT GLAS OFFSHORE WIND FARM LIMITED, Offshore wind, Gate 1Oct 2031300 MW
- Merlin 2 Offshore WindfarmOFFSHORE WIND LIMITED, Offshore wind, Gate 1Oct 20311.5 GW
- Morwind 300Morwind Ltd, Offshore wind, Not statedOct 2031300 MW
- Cormoran Offshore Wind FarmSouth West Wind Holdco Limited, Offshore wind, Not statedDec 20361 GW
- Equinor Celtic Sea 1EQUINOR NEW ENERGY LIMITED, Offshore wind, Gate 1Dec 20361 GW
- GallosCorio Generation Limited, Offshore wind, Not statedDec 20362 GW