Burwell (Tertiary)
- Connection date
- 30 Jun 2029
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001109
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jun 2023 registerCapacity changed from 49.9 MW to 57 MW
- 30 Jun 2023 registerConnection date moved from 1 Nov 2022 to 30 Jun 2029 (+80 months)
- 23 Dec 2022 registerConnection point changed from Burwell 400kV to Burwell Main 400kV Substation
- 26 Feb 2021 registerConnection date moved from 11 Jan 2022 to 1 Nov 2022 (+10 months)
Also at Burwell Main 400kV Substation
Substation view1 other project, 57 MW still to connect at this substation in total.