Tottenham

PIVOTED POWER LLP at Tottenham GSP

Connection date
Left 28 Jun 2024
Gate
Not stated
Status
Scoping
Technology
Storage
Total capacity
49.9 MW
Connected now
0 MW
Still to connect
49.9 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001060
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 28 Jun 2024 register
    Left the register (49.9 MW from 31 Oct 2024)
  • 23 Dec 2022 register
    Substation name updated in the register (from Tottenham to Tottenham GSP)
  • 25 Feb 2022 register
    Connection date moved from 2 Jan 2023 to 31 Oct 2024 (+22 months)
  • 26 Feb 2021 register
    Substation name updated in the register (from Tottenham 275kV to Tottenham)
  • 26 Feb 2021 register
    Connection date moved from 1 Feb 2023 to 2 Jan 2023 (−1 month)

Also at Tottenham GSP

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO