Kemsley
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 20 Sep 2019
Swale, reference 19/502514/FULL · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 49.9 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000235
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Dec 2022 registerConnection point changed from Kemsley 400/132kV Substation to Kemsley 400kV Substation
- 30 Mar 2022 registerConnection date removed (was 18 Jan 2021)
- 25 Feb 2022 registerConnection date set to 18 Jan 2021
- 30 Mar 2021 register49.9 MW now connected
- 30 Mar 2021 registerStatus changed from Awaiting Consents to Built
Also at Kemsley 400kV Substation
Substation view1 other project, 249 MW still to connect at this substation in total.