Projects / Substation
Indian Queens 400kV Substation
England and Wales, National Grid Electricity Transmission
5projects in the register
580 MWstill to connect
47.5 MWof that with Gate 2 offers
140 MWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Indian Queens | PIVOTED POWER LLP | Storage | 47.5 | 30 Jul 2024 Past date | Not stated | Consented |
| St Dennis Hendra | SAMBAR POWER LIMITED | Storage | 47.5 | 31 Oct 2024 Past date | Not stated | Consented |
| Indian Queens Energy Centre | IQ ENERGY CENTRE LIMITED | Storage with solar or wind | 47.5 | 30 May 2027 | Gate 2 | Consented |
| Indian Queens | GRIDMOVE LTD | Storage with solar or wind | 437 | 31 Oct 2031 | Gate 1 | Scoping |
| Indian Queens | INDIAN QUEENS POWER LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Indian Queens Energy CentreEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose