Spennymoor 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Spennymoor | PIVOTED POWER LLP | Storage | 49.9 | 31 Oct 2028 | Gate 1 | Awaiting Consents |
| Spennymoor PV & BESS | CSE27 LIMITED | Storage with solar or wind | 49.9 | 30 Jul 2032 | Not stated | Scoping |
| Spennymoor Greener Grid Park | Spennymoor Grid Solutions Limited | Storage | 500 | 30 Oct 2035 | Not stated | Scoping |
| Spennymoor PV & BESS Sub | O&G Solar (SPV 20) Limited | Storage with solar or wind | 250 | 30 Oct 2035 | Not stated | Scoping |
Recent changes
- Spennymoor Greener Grid ParkEngland and Wales, StorageCustomer changed from Statkraft UK Ltd to Spennymoor Grid Solutions Limited
- SpennymoorEngland and Wales, StorageMarked as Gate 1
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windRenamed from Spennymoor BESS
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2032 to 30 Jul 2032 (+1 month)+1 mo
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- Spennymoor Greener Grid ParkEngland and Wales, StorageStage 1: Status changed from Scoping to Awaiting Consents
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 49.9 MW
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windConnection date moved from 30 Jul 2032 to 30 Jun 2032 (−1 month)−1 mo
- Spennymoor PV & BESS SubEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- Spennymoor Greener Grid ParkEngland and Wales, StorageStage 2: Connection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- Spennymoor PV & BESS SubEngland and Wales, Storage with solar or windAdded to the registerNew
- SpennymoorEngland and Wales, StorageConnection date moved from 31 Oct 2023 to 31 Oct 2028 (+60 months)+60 mo
- Spennymoor Greener Grid ParkEngland and Wales, StorageRestructured from 1 stage (0 MW from 30 Oct 2026) to 2 stages (0 MW from 29 Oct 2027, 500 MW from 31 Oct 2033)
- Spennymoor PV & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- SpennymoorEngland and Wales, StorageSubstation name updated in the register (from Spennymoor 400kV to Spennymoor 400kV Substation)
- Spennymoor Greener Grid ParkEngland and Wales, StorageSubstation name updated in the register (from Spennymoor 400kV to Spennymoor 400kV Substation)
- Spennymoor Greener Grid ParkEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?