Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Spennymoor 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
850 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
SpennymoorPIVOTED POWER LLPStorage49.931 Oct 2028Gate 1Awaiting Consents
Spennymoor PV & BESSCSE27 LIMITEDStorage with solar or wind49.930 Jul 2032Not statedScoping
Spennymoor Greener Grid ParkSpennymoor Grid Solutions LimitedStorage50030 Oct 2035Not statedScoping
Spennymoor PV & BESS SubO&G Solar (SPV 20) LimitedStorage with solar or wind25030 Oct 2035Not statedScoping

Recent changes

  • Spennymoor Greener Grid ParkEngland and Wales, StorageCustomer changed from Statkraft UK Ltd to Spennymoor Grid Solutions Limited
  • SpennymoorEngland and Wales, StorageMarked as Gate 1
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windRenamed from Spennymoor BESS
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2032 to 30 Jul 2032 (+1 month)+1 mo
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
  • Spennymoor Greener Grid ParkEngland and Wales, StorageStage 1: Status changed from Scoping to Awaiting Consents
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 49.9 MW
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windConnection date moved from 30 Jul 2032 to 30 Jun 2032 (−1 month)−1 mo
  • Spennymoor PV & BESS SubEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
  • Spennymoor Greener Grid ParkEngland and Wales, StorageStage 2: Connection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
  • Spennymoor PV & BESS SubEngland and Wales, Storage with solar or windAdded to the registerNew
  • SpennymoorEngland and Wales, StorageConnection date moved from 31 Oct 2023 to 31 Oct 2028 (+60 months)+60 mo
  • Spennymoor Greener Grid ParkEngland and Wales, StorageRestructured from 1 stage (0 MW from 30 Oct 2026) to 2 stages (0 MW from 29 Oct 2027, 500 MW from 31 Oct 2033)
  • Spennymoor PV & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
  • SpennymoorEngland and Wales, StorageSubstation name updated in the register (from Spennymoor 400kV to Spennymoor 400kV Substation)
  • Spennymoor Greener Grid ParkEngland and Wales, StorageSubstation name updated in the register (from Spennymoor 400kV to Spennymoor 400kV Substation)
  • Spennymoor Greener Grid ParkEngland and Wales, StorageAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO