Mannington
- Connection date
- 30 Nov 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001091
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerTechnology changed from Storage to Storage, Solar
- 30 May 2025 registerStatus changed from Awaiting Consents to Consents Approved
- 31 Jan 2025 registerCapacity changed from 49.9 MW to 47.5 MW
- 29 Oct 2024 registerCapacity changed from 47.5 MW to 49.9 MW
- 28 Jun 2024 registerCapacity changed from 49.9 MW to 47.5 MW
- 28 Jun 2024 registerConnection date moved from 31 Oct 2024 to 30 Nov 2025 (+13 months)
- 28 Jul 2023 registerSubstation name updated in the register (from Mannington GSP to Mannington 400kV Substation)
- 28 Oct 2022 registerSubstation name updated in the register (from Mannington to Mannington GSP)
- 25 Feb 2022 registerConnection date moved from 30 Apr 2024 to 31 Oct 2024 (+6 months)
Also at Mannington 400kV Substation
Substation view2 other projects, 143 MW still to connect at this substation in total. 47.5 MW is due to connect here before this project’s connection date of 30 Nov 2025.