Kearsley
- Connection date
- 31 Oct 2028
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Demand + Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001064
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerMarked as Gate 1
- 30 Sep 2025 registerConnection point changed from Kearsley 400kV Substation to Kearsley 275kV Substation
- 29 Aug 2025 registerTechnology changed from Storage to Demand, Storage
- 23 Dec 2022 registerSubstation name updated in the register (from Kearsley 400kV to Kearsley 400kV Substation)
- 25 Feb 2022 registerConnection date moved from 31 Oct 2022 to 31 Oct 2028 (+72 months)
Also at Kearsley 275kV Substation
Substation view1 other project, 450 MW still to connect at this substation in total.