Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Willington East 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
402 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
WillingtonPIVOTED POWER LLPStorage5730 Jun 2026 Past dateGate 1Scoping
Willington East 1 (Tertiary)ENSO GREEN HOLDINGS U LIMITEDStorage with solar or wind47.530 Oct 2027Gate 1Scoping
Willington East 2 (Tertiary)ENSO GREEN HOLDINGS SS LIMITEDStorage with solar or wind47.530 Jul 2028Gate 1Scoping
Willington PV & BESSWILLINGTON ENERGY PARK LIMITEDStorage with solar or wind25031 Oct 2033Gate 1Scoping

Left the register since January 2021: Willington (2 GW).

Recent changes

  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington East 400/33kV Substation to Willington East 400kV Substation
  • Willington East 2 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington East 400/33kV Substation to Willington East 400kV Substation
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
  • Willington East 2 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington 400kV Substation to Willington East 400/33kV Substation
  • Willington East 2 (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windGate marking removed (was Gate 1)
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington 400kV Substation to Willington East 400/33kV Substation
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
  • Willington PV & BESSEngland and Wales, Storage with solar or windMarked as Gate 1
  • WillingtonEngland and Wales, StorageMarked as Gate 1
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS U LIMITED
  • Willington East 2 (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO Green Holdings SS Limited
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 30 Jun 2025, 7.1 MW from 30 Jun 2027) to 1 stage (47.5 MW from 30 Oct 2027). First connection date +28 months+28 mo
  • Willington East 2 (Tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (47.5 MW from 30 Jul 2028). First connection date +33 months+33 mo
  • Willington PV & BESSEngland and Wales, Storage with solar or windCustomer changed from O&G Solar (SPV 45) Limited to WILLINGTON ENERGY PARK LIMITED
  • Willington PV & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
  • WillingtonEngland and Wales, StorageCapacity changed from 49.9 MW to 57 MW
  • WillingtonEngland and Wales, StorageConnection date moved from 31 Oct 2022 to 30 Jun 2026 (+44 months)+44 mo
  • WillingtonEngland and Wales, StorageSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
  • Willington East 1 (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
  • Willington East 2 (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
  • WillingtonEngland and Wales, Thermal (gas, biomass, waste)Left the register (317 MW from 4 Jan 2021, 828 MW from 2 Jan 2022, 828 MW from 4 Jan 2022)1,973 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO