Willington East 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Willington | PIVOTED POWER LLP | Storage | 57 | 30 Jun 2026 Past date | Gate 1 | Scoping |
| Willington East 1 (Tertiary) | ENSO GREEN HOLDINGS U LIMITED | Storage with solar or wind | 47.5 | 30 Oct 2027 | Gate 1 | Scoping |
| Willington East 2 (Tertiary) | ENSO GREEN HOLDINGS SS LIMITED | Storage with solar or wind | 47.5 | 30 Jul 2028 | Gate 1 | Scoping |
| Willington PV & BESS | WILLINGTON ENERGY PARK LIMITED | Storage with solar or wind | 250 | 31 Oct 2033 | Gate 1 | Scoping |
Left the register since January 2021: Willington (2 GW).
Recent changes
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington East 400/33kV Substation to Willington East 400kV Substation
- Willington East 2 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington East 400/33kV Substation to Willington East 400kV Substation
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
- Willington East 2 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington 400kV Substation to Willington East 400/33kV Substation
- Willington East 2 (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windGate marking removed (was Gate 1)
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windConnection point changed from Willington 400kV Substation to Willington East 400/33kV Substation
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
- Willington PV & BESSEngland and Wales, Storage with solar or windMarked as Gate 1
- WillingtonEngland and Wales, StorageMarked as Gate 1
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS U LIMITED
- Willington East 2 (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO Green Holdings SS Limited
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 30 Jun 2025, 7.1 MW from 30 Jun 2027) to 1 stage (47.5 MW from 30 Oct 2027). First connection date +28 months+28 mo
- Willington East 2 (Tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (47.5 MW from 30 Jul 2028). First connection date +33 months+33 mo
- Willington PV & BESSEngland and Wales, Storage with solar or windCustomer changed from O&G Solar (SPV 45) Limited to WILLINGTON ENERGY PARK LIMITED
- Willington PV & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- WillingtonEngland and Wales, StorageCapacity changed from 49.9 MW to 57 MW
- WillingtonEngland and Wales, StorageConnection date moved from 31 Oct 2022 to 30 Jun 2026 (+44 months)+44 mo
- WillingtonEngland and Wales, StorageSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
- Willington East 1 (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
- Willington East 2 (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Willington East 400kV to Willington East 400kV Substation)
- WillingtonEngland and Wales, Thermal (gas, biomass, waste)Left the register (317 MW from 4 Jan 2021, 828 MW from 2 Jan 2022, 828 MW from 4 Jan 2022)1,973 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?