QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Projects / England and Wales
Connection date
31 Oct 2031
Gate
Gate 1
Status
Awaiting consent
Technology
Storage
Total capacity
100 MW
Connected now
0 MW
Still to connect
100 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001073
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1049.949.931 Oct 2031Gate 1Awaiting consent
2050.110031 Oct 2037Gate 1Awaiting consent

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at Taunton 400kV Substation

Substation view

No other projects in the register at this connection point.