Taunton
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001073
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 31 Oct 2031 | Gate 1 | Awaiting Consents |
| 2 | 0 | 50.1 | 100 | 31 Oct 2037 | Gate 1 | Awaiting Consents |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Apr 2026 registerStage 1: Marked as Gate 1
- 17 Apr 2026 registerStage 2: Marked as Gate 1
- 27 Aug 2024 registerStage 1: Connection date moved from 31 Oct 2029 to 31 Oct 2031 (+24 months)
- 27 Aug 2024 registerStage 2: Connection date moved from 31 Oct 2036 to 31 Oct 2037 (+12 months)
- 28 Jul 2023 registerRestructured from 1 stage (49.9 MW from 31 Oct 2023) to 2 stages (49.9 MW from 31 Oct 2029, 50.1 MW from 31 Oct 2036). First connection date +72 months
- 23 Dec 2022 registerSubstation name updated in the register (from Taunton to Taunton GSP)
Also at Taunton 400kV Substation
Substation viewNo other projects in the register at this connection point.