Oldbury (Tertiary)
- Connection date
- 30 Jun 2027
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001074
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 30 Jun 2027 | Gate 1 | Awaiting Consents |
| 2 | 0 | 7.1 | 57 | 31 Oct 2037 | Gate 1 | Awaiting Consents |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Dec 2025 registerStage 1: Marked as Gate 1
- 12 Dec 2025 registerStage 2: Marked as Gate 1
- 28 Jun 2024 registerRestructured from 1 stage (49.9 MW from 1 Nov 2025) to 2 stages (49.9 MW from 30 Jun 2027, 7.1 MW from 31 Oct 2037). First connection date +20 months
- 23 Dec 2022 registerSubstation name updated in the register (from Oldbury 275kV to Oldbury 275kV Substation)
- 26 Feb 2021 registerConnection date moved from 11 Jan 2025 to 1 Nov 2025 (+10 months)
Also at Oldbury 275kV Substation
Substation viewNo other projects in the register at this connection point.