Harker 400/132KV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Pivot Power Harker Hybrid | PIVOTED POWER LLP | Storage with solar or wind | 57 | 31 Oct 2029 | Gate 1 | Scoping |
Recent changes
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windStatus changed from Consents Approved to Scoping
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windConnection point changed from Harker 400kV Substation to Harker 400/132KV Substation
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windMarked as Gate 1
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windCapacity changed from 49.9 MW to 57 MW
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 31 Oct 2029 (+60 months)+60 mo
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windSubstation name updated in the register (from Harker 400kV to Harker 400kV Substation)
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windRenamed from Harker
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?