Projects / Substation
Bolney 400kV Substation
England and Wales, National Grid Electricity Transmission
6projects in the register
1.5 GWstill to connect
0 MWof that with Gate 2 offers
460 MWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bolney (tertiary) | BOLNEY GREEN LIMITED | Storage with solar or wind | 57 | 29 May 2028 | Gate 1 | Scoping |
| Rampion Extension Offshore Wind Farm | RAMPION EXTENSION DEVELOPMENT LIMITED | Offshore wind | 1,200 | 31 Dec 2029 +41 mo | Not stated | Scoping |
| Bolney | PIVOTED POWER LLP | Storage with solar or wind | 47.5 | 31 Jan 2031 | Not stated | Scoping |
| Bolney Grid Stability Services | WP GRID SERVICES 13 LIMITED | Other | 0 | 31 Oct 2031 (0 MW) | Not stated | Scoping |
| Bolney Farm | Dragon Green 2 Renewables Ltd | Storage with solar or wind | 200 | 30 Oct 2037 | Gate 1 | Scoping |
| Shoreham | VPI Power Limited | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Rampion Extension Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Aug 2026 to 31 Dec 2029 (+41 months)+41 mo
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose