Whitson
- Connection date
- 31 Oct 2027
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001061
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Dec 2025 registerMarked as Gate 1
- 21 Nov 2025 registerConnection date moved from 31 Oct 2026 to 31 Oct 2027 (+12 months)
- 30 May 2023 registerConnection point changed from Whitson 275/33kV Substation to Whitson 275kV Substation
- 23 Dec 2022 registerConnection point changed from Whitson 275kV to Whitson 275/33kV Substation
Also at Whitson 275kV Substation
Substation view3 other projects, 485 MW still to connect at this substation in total.