Spennymoor
- Connection date
- 31 Oct 2028
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001138
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Apr 2026 registerMarked as Gate 1
- 30 Jan 2024 registerConnection date moved from 31 Oct 2023 to 31 Oct 2028 (+60 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Spennymoor 400kV to Spennymoor 400kV Substation)
Also at Spennymoor 400kV Substation
Substation view3 other projects, 850 MW still to connect at this substation in total.