Kirkby 275/33kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Kirkby (Tertiary) | PIVOTED POWER LLP | Storage with solar or wind | 57 | 30 Aug 2027 | Gate 1 | Scoping |
| Kirkby | KIRKBY BATTERY STORAGE LTD | Storage | 57 | 31 Oct 2027 +25 mo | Gate 2 | Consents Approved |
Recent changes
- KirkbyEngland and Wales, StorageStage 2: Gate marking removed (was Gate 2)
- KirkbyEngland and Wales, StorageStage 1: Given a Gate 2 connection offerGate 2
- KirkbyEngland and Wales, StorageStage 2: Status changed from Scoping to Consents Approved
- KirkbyEngland and Wales, StorageStage 2: Given a Gate 2 connection offerGate 2
- KirkbyEngland and Wales, StorageConnection point changed from Kirkby 275kV Substation to Kirkby 275/33kV Substation
- KirkbyEngland and Wales, StorageStage 1: Connection date moved from 30 Sep 2025 to 31 Oct 2027 (+25 months)+25 mo
- Kirkby (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection point changed from Kirkby GSP (ENW) to Kirkby 275/33kV Substation
- KirkbyEngland and Wales, StorageCustomer changed from HD001KIR LTD to KIRKBY BATTERY STORAGE LTD
- KirkbyEngland and Wales, StorageStage 1: Technology changed from Gas engines to Storage
- KirkbyEngland and Wales, StorageStage 2: Technology changed from Gas engines to Storage
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2025 to 30 Aug 2027 (+22 months)+22 mo
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection point changed from Kirkby 275kV Substation to Kirkby GSP (ENW)
- Kirkby (Tertiary)England and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- KirkbyEngland and Wales, StorageRestructured from 1 stage (49.5 MW from 1 Oct 2023) to 2 stages (49.9 MW from 30 Sep 2025, 7.1 MW from 30 Oct 2037). First connection date +24 months+24 mo
- Kirkby (Tertiary)England and Wales, Storage with solar or windCapacity changed from 49.9 MW to 57 MW
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection date moved from 1 Nov 2022 to 31 Oct 2025 (+36 months)+36 mo
- KirkbyEngland and Wales, StorageRenamed from Coopers Lane Kirkby
- KirkbyEngland and Wales, StorageTechnology changed from Gas (CCGT) to Gas engines
- KirkbyEngland and Wales, StorageSubstation name updated in the register (from Kirkby 275kV to Kirkby 275kV Substation)
- Kirkby (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Kirkby 275kV to Kirkby 275kV Substation)
- KirkbyEngland and Wales, StorageConnection date moved from 30 Oct 2022 to 1 Oct 2023 (+11 months)+11 mo
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection date moved from 11 Jan 2022 to 1 Nov 2022 (+10 months)+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?