Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

ScottishPower Renewables (UK) Limited

Customer named in the TEC register

34projects in the register
5.3 GWstill to connect
0 MWof that with Gate 2 offers
1.6 GWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Arecleoch Extension WindfarmArecleoch 132/33kVOnshore wind72.831 Aug 2026 Past dateNot statedScoping
Whitelee ExtensionWhitelee Extension 275/33kVStorage with solar or wind32.01 Dec 2026Not statedBuilt
Dersalloch Wind Farm ExtensionDersalloch 132/33kVStorage11.031 Oct 2027Not statedScoping
HarestanesHarestanes West Wind Farm 132/33kVStorage with solar or wind38.331 Mar 2028Not statedUnder Construction/Commissioning
Harestanes West Wind FarmHarestanes West Wind Farm 132/33kVOnshore wind81.01 Sep 2029Not statedScoping
Beinn Tharsuinn RepowerBEINN THURSUNN REPOWER 275/33KVOnshore wind84.031 Oct 2029Gate 1Scoping
Carrick Wind FarmCarrick Wind Farm SubstationOnshore wind84.01 Apr 2030Not statedAwaiting Consents
Hollandmey Renewable Energy DevelopmentHollandmey Renewable Energy Development132/33kV SubstationOnshore wind49.531 May 2030Not statedConsents Approved
Euchanhead Wind FarmEuchanhead 132kV SubstationOnshore wind11229 Oct 2030Not statedAwaiting Consents
Earraghail Renewable Energy Development (formerly Skipness & Corranbuie)Earraghail 275/33KV SubstationStorage with solar or wind1051 Apr 2031Gate 1Scoping
WhiteleeWhitelee 275/33kVOnshore wind5132 May 2031Not statedScoping
Wether HillWether Hill 132/33KV SubstationOnshore wind66.029 Sep 2031Gate 1Scoping
Fasque WindfarmFetteresso 132kV substationOnshore wind10531 Oct 2031Gate 1Scoping
Hare Hill RepoweringHare Hill Repowering 132/33kV SubstationOnshore wind11431 Oct 2031Gate 1Scoping
Dunlaw ExtensionDunlaw Extension 132/33kVOnshore wind1261 Apr 2032Not statedBuilt
Sheirdrim Wind FarmSheirdrim 132kV SubstationOnshore wind84.01 Apr 2032Gate 1Scoping
ArecleochArecleoch 132/33kVOnshore wind21615 Jun 2032Not statedScoping
BlacklawBlacklaw 132/33kVStorage with solar or wind2228 Oct 2032Not statedScoping
Clauchrie WindfarmClauchrie 132/33KV SubstationStorage with solar or wind10830 Jan 2033 −4 moGate 1Scoping
Machair Offshore Wind FarmMachair 275/66kV Offshore SubstationOffshore wind2,00016 Sep 2033Not statedScoping
Beinn an Tuirc 1Beinn an Tuirc SubstationOnshore wind95.231 Oct 2034Gate 1Scoping
SPR CS1SPR CS1 275/66KV OFFSHORE SUBSTATIONOffshore wind1,00031 Oct 2037Gate 1Scoping
ArdkinglasArdkinglas GSPOnshore wind0.0ConnectedNot statedBuilt
Beinn an Tuirc 2Carradale 1 GSPOnshore wind0.0ConnectedNot statedBuilt
Beinn an Tuirc 3Carradale 1 GSPOnshore wind0.0ConnectedNot statedBuilt
Beinn TharsuinnAlness GSPOnshore wind0.0ConnectedNot statedBuilt
Blacklaw ExtensionBlacklaw Extension 132/33kVStorage with solar or wind0.0ConnectedNot statedBuilt
Dersalloch Wind FarmDersalloch 132/33kVOnshore wind0.0ConnectedNot statedBuilt
Ewe HillEwehill 132/33kVOnshore wind0.0ConnectedNot statedBuilt
Glen App WindfarmGlen App 33kVOnshore wind0.0ConnectedNot statedBuilt
Halsary Wind FarmMybster 3 33kV SubstationOnshore wind0.0ConnectedNot statedBuilt
Hare Hill Extension Wind FarmCoylton 132/33kVOnshore wind0.0ConnectedNot statedBuilt
Kilgallioch Wind FarmKilgallioch 275kV SubstationOnshore wind0.0ConnectedNot statedBuilt
Mark Hill Wind FarmMark Hill 275/132kVOnshore wind0.0ConnectedNot statedBuilt

Left the register since January 2021: OWF2 (2 GW).

Recent changes

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO