Sheirdrim Wind Farm
Scottish Power Renewables (UK) Limited at Sheirdrim 132kV Substation
- Connection date
- 1 Apr 2032
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Refused on appeal 26 Jun 2023
Scottish Government (S36), reference ECU00001957 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 84 MW
- Connected now
- 0 MW
- Still to connect
- 84 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001066
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Mar 2032 to 1 Apr 2032 (2 days later)
- 10 Oct 2026 registerConnection date moved from 1 Apr 2032 to 30 Mar 2032 (2 days earlier)
- 10 Oct 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection date moved from 31 Oct 2029 to 1 Apr 2032 (+29 months)
- 30 Jan 2024 registerConnection date moved from 30 Apr 2026 to 31 Oct 2029 (+42 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Sheirdrim 132kV to Sheirdrim 132kV Substation)
- 30 Mar 2022 registerConnection date moved from 30 Apr 2025 to 30 Apr 2026 (+12 months)
Also at Sheirdrim 132kV Substation
Substation viewNo other projects in the register at this connection point.