Kilgallioch 275kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Kilgallioch Wind Farm | Scottish Power Renewables (UK) Limited | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Kilgallioch Wind FarmSouth Scotland, Onshore windRestructured from 2 stages (228 MW connected, 46 MW connected) to 1 stage (274 MW connected)
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: 46 MW now connectedConnected
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Gate marking removed (was Gate 2)
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Status changed from Consents Approved to Built
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Given a Gate 2 connection offerGate 2
- Kilgallioch Wind FarmSouth Scotland, Onshore windRenamed from Kilgallioch Wind Farm and Kilgallioch Wind Farm Extension - Turbines
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Connection date moved from 30 Apr 2024 to 8 Apr 2025 (+11 months)+11 mo
- Kilgallioch Wind FarmSouth Scotland, Onshore windRenamed from Kilgallioch
- Kilgallioch Wind FarmSouth Scotland, Onshore windConnection point changed from Kilgallioch 132/33kV Substation to Kilgallioch 275kV Substation
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Connection date moved from 30 Apr 2022 to 30 Apr 2024 (+24 months)+24 mo
- Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Connection date moved from 31 Oct 2022 to 30 Apr 2022 (−6 months)−6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?