Beinn an Tuirc 1
Scottish Power Renewables (UK) Limited at Beinn an Tuirc Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 95.2 MW
- Connected now
- 0 MW
- Still to connect
- 95.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-003918
- In the register since
- December 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerMarked as Gate 1
- 12 Dec 2025 registerConnection point changed from Carradale 1 GSP to Beinn an Tuirc Substation
- 24 Dec 2024 registerAdded to the register
Also at Beinn an Tuirc Substation
Substation viewNo other projects in the register at this connection point.