Beinn an Tuirc 3
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 23 Feb 2017
Argyll and Bute, reference 15/03057/PP · Source: REPD - Technology
- Onshore wind
- Total capacity
- 50 MW
- Connected now
- 50 MW
- Still to connect
- 0 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000029
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Jan 2023 registerConnection point changed from Carradale GSP to Carradale 1 GSP
- 29 Jun 2021 registerRestructured from 2 stages (25 MW from 30 Apr 2021, 25 MW connected) to 1 stage (50 MW connected)
- 30 Apr 2021 registerStage 2: Connection date moved from 30 Sep 2021 to 30 Apr 2021 (−5 months)
- 30 Mar 2021 registerSubstation name updated in the register (from Carradale 132/33kV Substation to Carradale GSP)
- 26 Feb 2021 registerRestructured from 1 stage (25 MW from 30 Nov 2020) to 2 stages (25 MW from 30 Sep 2021, 25 MW connected). First connection date +10 months
Also at Carradale 1 GSP
Substation view3 other projects, 72.6 MW still to connect at this substation in total.