Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Beinn Tharsuinn Repower

Scottish Power Renewables (UK) Limited at BEINN THURSUNN REPOWER 275/33KV

Connection date
31 Oct 2029
Gate
Gate 1
Status
Scoping
Technology
Onshore wind
Total capacity
84 MW
Connected now
0 MW
Still to connect
84 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001035
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 17 Apr 2026 register
    Transmission owner changed from NGET to SHET
  • 7 Apr 2026 register
    Connection point changed from Beinn Tharsuinn Repower 132/33kV Substation to BEINN THURSUNN REPOWER 275/33KV
  • 7 Apr 2026 register
    Transmission owner changed from SHET to NGET
  • 7 Apr 2026 register
    Marked as Gate 1
  • 31 May 2024 register
    Renamed from Beinn Tharsuinn Extension
  • 31 May 2024 register
    Connection point changed from Beinn Tharsuinn Extension 132/33kV Substation to Beinn Tharsuinn Repower 132/33kV Substation
  • 29 Dec 2023 register
    Connection date moved from 1 Oct 2027 to 31 Oct 2029 (+25 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Beinn Tharsuinn Extension 132/33kV to Beinn Tharsuinn Extension 132/33kV Substation)
  • 29 Apr 2022 register
    Stage removed (0 MW)
  • 25 Feb 2022 register
    Restructured from 2 stages (44.8 MW from 1 Dec 2025, 39.2 MW from 1 Oct 2027) to 2 stages (84 MW from 1 Oct 2027, 0 MW). First connection date +22 months
  • 26 Feb 2021 register
    Stage 1: Connection date moved from 12 Jan 2025 to 1 Dec 2025 (+11 months)
  • 26 Feb 2021 register
    Stage 2: Connection date moved from 10 Jan 2027 to 1 Oct 2027 (+9 months)

Also at BEINN THURSUNN REPOWER 275/33KV

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO