Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Harestanes West Wind Farm 132/33kV

South Scotland, SP Energy Networks

2projects in the register
119 MWstill to connect
0 MWof that with Gate 2 offers
125 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
HarestanesScottish Power Renewables (UK) LimitedStorage with solar or wind38.331 Mar 2028Not statedUnder Construction/Commissioning
Harestanes West Wind FarmScottish Power Renewables (UK) LimitedOnshore wind811 Sep 2029Not statedScoping

Recent changes

  • HarestanesSouth Scotland, Storage with solar or windConnection point changed from Harestanes 132/33kV to Harestanes West Wind Farm 132/33kV
  • Harestanes West Wind FarmSouth Scotland, Onshore windConnection point changed from Old Forest of Ae 33kV Substation to Harestanes West Wind Farm 132/33kV
  • Harestanes West Wind FarmSouth Scotland, Onshore windRestructured from 1 stage (56 MW from 31 Oct 2027) to 2 stages (56 MW from 1 Sep 2029, 25 MW from 1 Jul 2035). First connection date +22 months+22 mo
  • Harestanes West Wind FarmSouth Scotland, Onshore windRenamed from Old Forest of Ae
  • HarestanesSouth Scotland, Storage with solar or windStage 1: Technology changed from Onshore wind to Storage, Onshore wind
  • HarestanesSouth Scotland, Storage with solar or windStage 2: Technology changed from Onshore wind to Storage, Onshore wind
  • HarestanesSouth Scotland, Storage with solar or windConnection point changed from Harestanes 132kV Substation to Harestanes 132/33kV
  • HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 1 Mar 2025 to 31 Mar 2028 (+37 months)+37 mo
  • HarestanesSouth Scotland, Storage with solar or windSubstation name updated in the register (from Harestanes to Harestanes 132kV Substation)
  • Harestanes West Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Old Forest of Ae 33kV to Old Forest of Ae 33kV Substation)
  • HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 1 Apr 2022 to 1 Mar 2025 (+35 months)+35 mo
  • HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 1 Nov 2021 to 1 Apr 2022 (+5 months)+5 mo
  • HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 11 Jan 2021 to 1 Nov 2021 (+10 months)+10 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO