Harestanes West Wind Farm 132/33kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Harestanes | Scottish Power Renewables (UK) Limited | Storage with solar or wind | 38.3 | 31 Mar 2028 | Not stated | Under Construction/Commissioning |
| Harestanes West Wind Farm | Scottish Power Renewables (UK) Limited | Onshore wind | 81 | 1 Sep 2029 | Not stated | Scoping |
Recent changes
- HarestanesSouth Scotland, Storage with solar or windConnection point changed from Harestanes 132/33kV to Harestanes West Wind Farm 132/33kV
- Harestanes West Wind FarmSouth Scotland, Onshore windConnection point changed from Old Forest of Ae 33kV Substation to Harestanes West Wind Farm 132/33kV
- Harestanes West Wind FarmSouth Scotland, Onshore windRestructured from 1 stage (56 MW from 31 Oct 2027) to 2 stages (56 MW from 1 Sep 2029, 25 MW from 1 Jul 2035). First connection date +22 months+22 mo
- Harestanes West Wind FarmSouth Scotland, Onshore windRenamed from Old Forest of Ae
- HarestanesSouth Scotland, Storage with solar or windStage 1: Technology changed from Onshore wind to Storage, Onshore wind
- HarestanesSouth Scotland, Storage with solar or windStage 2: Technology changed from Onshore wind to Storage, Onshore wind
- HarestanesSouth Scotland, Storage with solar or windConnection point changed from Harestanes 132kV Substation to Harestanes 132/33kV
- HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 1 Mar 2025 to 31 Mar 2028 (+37 months)+37 mo
- HarestanesSouth Scotland, Storage with solar or windSubstation name updated in the register (from Harestanes to Harestanes 132kV Substation)
- Harestanes West Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Old Forest of Ae 33kV to Old Forest of Ae 33kV Substation)
- HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 1 Apr 2022 to 1 Mar 2025 (+35 months)+35 mo
- HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 1 Nov 2021 to 1 Apr 2022 (+5 months)+5 mo
- HarestanesSouth Scotland, Storage with solar or windStage 2: Connection date moved from 11 Jan 2021 to 1 Nov 2021 (+10 months)+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?