BEINN THURSUNN REPOWER 275/33KV
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Beinn Tharsuinn Repower | Scottish Power Renewables (UK) Limited | Onshore wind | 84 | 31 Oct 2029 | Gate 1 | Scoping |
Recent changes
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windTransmission owner changed from NGET to SHET
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windConnection point changed from Beinn Tharsuinn Repower 132/33kV Substation to BEINN THURSUNN REPOWER 275/33KV
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windTransmission owner changed from SHET to NGET
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windMarked as Gate 1
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windRenamed from Beinn Tharsuinn Extension
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windConnection point changed from Beinn Tharsuinn Extension 132/33kV Substation to Beinn Tharsuinn Repower 132/33kV Substation
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windConnection date moved from 1 Oct 2027 to 31 Oct 2029 (+25 months)+25 mo
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windSubstation name updated in the register (from Beinn Tharsuinn Extension 132/33kV to Beinn Tharsuinn Extension 132/33kV Substation)
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windStage removed (0 MW)
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windRestructured from 2 stages (44.8 MW from 1 Dec 2025, 39.2 MW from 1 Oct 2027) to 2 stages (84 MW from 1 Oct 2027, 0 MW). First connection date +22 months+22 mo
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windStage 1: Connection date moved from 12 Jan 2025 to 1 Dec 2025 (+11 months)+11 mo
- Beinn Tharsuinn RepowerNorth Scotland, Onshore windStage 2: Connection date moved from 10 Jan 2027 to 1 Oct 2027 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?