Carradale 1 GSP
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Narachan Wind Farm | ENERGYFARM UK NARACHAN LLP | Onshore wind | 72.6 | 30 Apr 2030 | Not stated | Scoping |
| Beinn an Tuirc 2 | Scottish Power Renewables (UK) Limited | Onshore wind | 0 | Connected | Not stated | Built |
| Beinn an Tuirc 3 | Scottish Power Renewables (UK) Limited | Onshore wind | 0 | Connected | Not stated | Built |
| Blary Hill Wind Farm | BLARY HILL ENERGY LIMITED | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Narachan Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Nov 2028 to 30 Apr 2030 (+17 months)+17 mo
- Narachan Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2027 to 30 Nov 2028 (+19 months)+19 mo
- Narachan Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- Beinn an Tuirc 2North Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
- Beinn an Tuirc 3North Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
- Blary Hill Wind FarmNorth Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
- Blary Hill Wind FarmNorth Scotland, Onshore wind35 MW now connectedConnected
- Blary Hill Wind FarmNorth Scotland, Onshore windStatus changed from Consents Approved to Built
- Blary Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2021 to 21 Jul 2021 (+3 months)+3 mo
- Beinn an Tuirc 3North Scotland, Onshore windRestructured from 2 stages (25 MW from 30 Apr 2021, 25 MW connected) to 1 stage (50 MW connected)
- Beinn an Tuirc 3North Scotland, Onshore windStage 2: Connection date moved from 30 Sep 2021 to 30 Apr 2021 (−5 months)−5 mo
- Beinn an Tuirc 2North Scotland, Onshore windSubstation name updated in the register (from Carradale to Carradale GSP)
- Beinn an Tuirc 3North Scotland, Onshore windSubstation name updated in the register (from Carradale 132/33kV Substation to Carradale GSP)
- Blary Hill Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Carradale to Carradale GSP)
- Beinn an Tuirc 3North Scotland, Onshore windRestructured from 1 stage (25 MW from 30 Nov 2020) to 2 stages (25 MW from 30 Sep 2021, 25 MW connected). First connection date +10 months+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?