Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Carradale 1 GSP

North Scotland, SSEN Transmission

4projects in the register
72.6 MWstill to connect
0 MWof that with Gate 2 offers
129 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Narachan Wind FarmENERGYFARM UK NARACHAN LLPOnshore wind72.630 Apr 2030Not statedScoping
Beinn an Tuirc 2Scottish Power Renewables (UK) LimitedOnshore wind0ConnectedNot statedBuilt
Beinn an Tuirc 3Scottish Power Renewables (UK) LimitedOnshore wind0ConnectedNot statedBuilt
Blary Hill Wind FarmBLARY HILL ENERGY LIMITEDOnshore wind0ConnectedNot statedBuilt

Recent changes

  • Narachan Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Nov 2028 to 30 Apr 2030 (+17 months)+17 mo
  • Narachan Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2027 to 30 Nov 2028 (+19 months)+19 mo
  • Narachan Wind FarmNorth Scotland, Onshore windAdded to the registerNew
  • Beinn an Tuirc 2North Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
  • Beinn an Tuirc 3North Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
  • Blary Hill Wind FarmNorth Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
  • Blary Hill Wind FarmNorth Scotland, Onshore wind35 MW now connectedConnected
  • Blary Hill Wind FarmNorth Scotland, Onshore windStatus changed from Consents Approved to Built
  • Blary Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2021 to 21 Jul 2021 (+3 months)+3 mo
  • Beinn an Tuirc 3North Scotland, Onshore windRestructured from 2 stages (25 MW from 30 Apr 2021, 25 MW connected) to 1 stage (50 MW connected)
  • Beinn an Tuirc 3North Scotland, Onshore windStage 2: Connection date moved from 30 Sep 2021 to 30 Apr 2021 (−5 months)−5 mo
  • Beinn an Tuirc 2North Scotland, Onshore windSubstation name updated in the register (from Carradale to Carradale GSP)
  • Beinn an Tuirc 3North Scotland, Onshore windSubstation name updated in the register (from Carradale 132/33kV Substation to Carradale GSP)
  • Blary Hill Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Carradale to Carradale GSP)
  • Beinn an Tuirc 3North Scotland, Onshore windRestructured from 1 stage (25 MW from 30 Nov 2020) to 2 stages (25 MW from 30 Sep 2021, 25 MW connected). First connection date +10 months+10 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO