Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland
Connection date
Increase at an existing station: +32 MW from 1 Dec 2026
Gate
Not stated
Status
Built
Technology
Storage + Hydrogen + Solar + Onshore wind
Total capacity
238 MW
Connected now
206 MW
Still to connect
32 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000068
In the register since
January 2021 or earlier

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Aug 2025 register
    Technology changed from Storage, Solar, Onshore wind to Storage, Solar, Onshore wind, Hydrogen
  • 28 Feb 2025 register
    Connection date moved from 31 Mar 2023 to 1 Dec 2026 (+44 months)
  • 31 Jan 2025 register
    Technology changed from Onshore wind to Storage, Solar, Onshore wind
  • 27 Sep 2024 register
    Substation name updated in the register (from Whitelee Extension to Whitelee Extension 275/33kV)
  • 30 Jun 2022 register
    Capacity changed from 0 MW to 32 MW
  • 30 Jun 2022 register
    Connection date set to 31 Mar 2023

Also at Whitelee Extension 275/33kV

Substation view

1 other project, 121 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO