Dersalloch Wind Farm
Scottish Power Renewables (UK) Limited at Dersalloch 132/33kV
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 23 Jul 2014
Scottish Government (S36) · Source: REPD - Technology
- Onshore wind
- Total capacity
- 69 MW
- Connected now
- 69 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000060
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerCapacity changed from 11 MW to 0 MW
- 30 Sep 2025 registerConnection date removed (was 31 Oct 2027)
- 27 Sep 2024 registerConnection point changed from Dersalloch 132kV Substation to Dersalloch 132/33kV
- 28 Jul 2023 registerCapacity changed from 16 MW to 11 MW
- 28 Apr 2023 registerCapacity changed from 0 MW to 16 MW
- 28 Apr 2023 registerConnection date set to 31 Oct 2027
- 23 Dec 2022 registerSubstation name updated in the register (from Dersalloch to Dersalloch 132kV Substation)
Also at Dersalloch 132/33kV
Substation view1 other project, 11 MW still to connect at this substation in total.