- Connection date
- 29 Sep 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 66 MW
- Connected now
- 0 MW
- Still to connect
- 66 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001527
- In the register since
- September 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection date moved from 1 Dec 2028 to 29 Sep 2031 (+34 months)
- 28 Sep 2021 registerAdded to the register
Also at Wether Hill 132/33KV Substation
Substation viewNo other projects in the register at this connection point.