- Connection date
- 31 Mar 2028
- Gate
- Not stated
- Status
- Under Construction/Commissioning
- Planning consent
- Granted 20 Dec 2019
Scottish Government (S36), reference ECU00001870 · Source: REPD - Technology
- Storage + Onshore wind
- Total capacity
- 163 MW
- Connected now
- 125 MW
- Still to connect
- 38.3 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000064
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 125 | 0 | 125 | None | Not stated | Built |
| 2 | 0 | 38.3 | 163.3 | 31 Mar 2028 | Not stated | Under Construction/Commissioning |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerConnection point changed from Harestanes 132/33kV to Harestanes West Wind Farm 132/33kV
- 29 Oct 2024 registerStage 1: Technology changed from Onshore wind to Storage, Onshore wind
- 29 Oct 2024 registerStage 2: Technology changed from Onshore wind to Storage, Onshore wind
- 27 Sep 2024 registerConnection point changed from Harestanes 132kV Substation to Harestanes 132/33kV
- 27 Sep 2024 registerStage 2: Connection date moved from 1 Mar 2025 to 31 Mar 2028 (+37 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Harestanes to Harestanes 132kV Substation)
- 28 Oct 2022 registerStage 2: Connection date moved from 1 Apr 2022 to 1 Mar 2025 (+35 months)
- 28 Jan 2022 registerStage 2: Connection date moved from 1 Nov 2021 to 1 Apr 2022 (+5 months)
- 26 Feb 2021 registerStage 2: Connection date moved from 11 Jan 2021 to 1 Nov 2021 (+10 months)
Also at Harestanes West Wind Farm 132/33kV
Substation view1 other project, 119 MW still to connect at this substation in total.