Euchanhead Wind Farm
Scottish Power Renewables (UK) Limited at Euchanhead 132kV Substation
- Connection date
- 29 Oct 2030
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 112 MW
- Connected now
- 0 MW
- Still to connect
- 112 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001011
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 27 Jun 2025 registerConnection date moved from 29 Oct 2029 to 29 Oct 2030 (+12 months)
- 30 May 2025 registerTechnology changed from Storage, Onshore wind to Onshore wind
- 31 Jan 2025 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 30 Jan 2024 registerConnection date moved from 29 Oct 2027 to 29 Oct 2029 (+24 months)
- 31 Mar 2023 registerConnection date moved from 30 Oct 2026 to 29 Oct 2027 (+12 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Euchanhead 132kV to Euchanhead 132kV Substation)
Also at Euchanhead 132kV Substation
Substation viewNo other projects in the register at this connection point.