Carrick Wind Farm Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Carrick Wind Farm | Scottish Power Renewables (UK) Limited | Onshore wind | 84 | 1 Apr 2030 | Not stated | Awaiting Consents |
Recent changes
- Carrick Wind FarmSouth Scotland, Onshore windStatus changed from Scoping to Awaiting Consents
- Carrick Wind FarmSouth Scotland, Onshore windConnection date moved from 28 Feb 2029 to 1 Apr 2030 (+13 months)+13 mo
- Carrick Wind FarmSouth Scotland, Onshore windConnection date moved from 30 Sep 2027 to 28 Feb 2029 (+17 months)+17 mo
- Carrick Wind FarmSouth Scotland, Onshore windConnection date moved from 30 Sep 2026 to 30 Sep 2027 (+12 months)+12 mo
- Carrick Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Carrick Wind Farm 275/33kV to Carrick Wind Farm Substation)
- Carrick Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Carrick Wind Farm to Carrick Wind Farm 275/33kV)
- Carrick Wind FarmSouth Scotland, Onshore windConnection date moved from 31 Jul 2025 to 30 Sep 2026 (+14 months)+14 mo
- Carrick Wind FarmSouth Scotland, Onshore windConnection date moved from 31 Jul 2024 to 31 Jul 2025 (+12 months)+12 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?