Distribution / SSEN / Grid supply point

MELKSHAM GSP

Grid supply point in Southern England (SEPD)

SSEN Embedded Capacity Register, November 2026 edition

96sites of 1 MW and over
1.9 GWcapacity
0.5 GWconnected (57 sites)
1.4 GWaccepted to connect (39 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar56746 MW313 MW433 MW
Storage10623 MW19 MW604 MW
Other or not stated10368 MW107 MW261 MW
Bioenergy and waste1379.1 MW35.6 MW43.5 MW
Gas and other fossil528.4 MW28.4 MW–
Wind111.4 MW11.4 MW–
Hydro and marine12.4 MW2.4 MW–

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
NORRINGTON23.8 MW26.6 MW
NORRINGTON327.7 MW–
NORRINGTON1–25.3 MW
NORRINGTON29.6 MW10.1 MW
NORRINGTON21.3 MW15 MW
NORRINGTON114.6 MW–
NORRINGTON114.3 MW–
NORRINGTON111.6 MW–
NORRINGTON19.5 MW–
NORRINGTON19.1 MW–
NORRINGTON17.3 MW–
NORRINGTON17.3 MW–
NORRINGTON17 MW–
NORRINGTON26.6 MW–
NORRINGTON15.2 MW–
NORRINGTON14.3 MW–
NORRINGTON14.3 MW–
NORRINGTON14.2 MW–
NORRINGTON1–1 MW
NORRINGTON1120 MW299 MW
CHIPPENHAM311.9 MW–
CHIPPENHAM111.4 MW–
CHIPPENHAM111.4 MW–
CHIPPENHAM111.4 MW–
CHIPPENHAM110.5 MW–
CHIPPENHAM1–10 MW
CHIPPENHAM16.7 MW–
CHIPPENHAM16.2 MW–
CHIPPENHAM15.8 MW–
CHIPPENHAM14.3 MW–
CHIPPENHAM14.3 MW–
CHIPPENHAM4–128 MW
ANDOVER130.4 MW–
ANDOVER221.1 MW–
ANDOVER1–20 MW
ANDOVER59.8 MW8.1 MW
ANDOVER2–17.2 MW
ANDOVER19.5 MW–
ANDOVER1–6.6 MW
ANDOVER14.4 MW–
ANDOVER13.3 MW–
ANDOVER1–2.4 MW
FROME19.5 MW–
FROME17.6 MW–
FROME17.2 MW–
FROME1–5.5 MW
FROME13.9 MW–
FROME13.6 MW–
FROME22.6 MW–
FROME12.4 MW–
FROME11.9 MW–
FROME11.9 MW–
FROME23.8 MW60 MW
WEST GRAFTON15.4 MW–
Not stated237.5 MW49.9 MW
Not stated1–49.9 MW
Not stated10100 MW606 MW

Search and filter all 96 sites at MELKSHAM GSP

Not found among the sites of 1 MW and over in SSEN’s November 2026 edition

1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 96 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

  • FACCOMBE ESTATENovember 2026 editionExport capacity changed from 2.425 MW to 0.53 MW
  • BRANSBURY MANOR FARMOctober 2026 editionExport capacity changed from 5.263 MW to 10 MW
  • BRANSBURY MANOR FARMSeptember 2026 editionExport capacity changed from 10 MW to 5.263 MW
  • FACCOMBE ESTATESeptember 2026 editionExport capacity changed from 0.53 MW to 2.425 MW
  • BLOUNTS COURT FARMJuly 2026 editionFlexible connection stated as “yes” (not stated in the June 2026 edition)
  • BRANSBURY MANOR FARMJuly 2026 editionExport capacity changed from 5.263 MW to 10 MW
  • BRANSBURY MANOR FARMJune 2026 editionExport capacity changed from 10 MW to 5.263 MW
  • FACCOMBE ESTATEApril 2026 editionExport capacity changed from 2.425 MW to 0.53 MW
  • BRANSBURY MANOR FARMFebruary 2026 editionExport capacity changed from 5 MW to 10 MW
  • FACCOMBE ESTATEFebruary 2026 editionExport capacity changed from 0.669 MW to 2.425 MW
  • LANDMARK FARMNovember 2025 editionTarget energisation date moved from 23 Sep 2024 to 23 Jan 2027 (28 months later)
  • CONRAD (MELKSHAM) LIMITEDOctober 2025 editionCustomer changed from CONRAD (MELKSHAM GSP) LIMITED to CONRAD (MELKSHAM) LIMITED
  • CONRAD (MELKSHAM) LIMITEDSeptember 2025 editionCustomer changed from CONRAD (MELKSHAM) LIMITED to CONRAD (MELKSHAM GSP) LIMITED
  • NORTHACRE RESOURCE RECOVERY PLANTJuly 2025 editionTechnology stated as Bioenergy and waste (not stated in the June 2025 edition)
  • UNIT 2July 2025 editionTechnology stated as Gas and other fossil (not stated in the June 2025 edition)
  • FORMER ANDOVER AIRFIELDApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
  • Site not namedApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
  • Site not namedApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
  • MONKLEY LANEJanuary 2025 editionCapacity changed from 2.5 MW to 55.91 MW
  • MONKLEY LANEJanuary 2025 editionExport capacity changed from 0.949 MW to 0 MW
  • LANDMARK FARMSeptember 2024 editionTarget energisation date stated as 23 Sep 2024 (not stated in the August 2024 edition)
  • BROOK FARM PVNovember 2023 editionCapacity stated as 3.8 MW (not stated in the October 2023 edition)
  • COWDOWN RENEWABLES LTDNovember 2023 editionCapacity changed from 47.368 MW to 30.4 MW
  • FORMER ANDOVER AIRFIELDNovember 2023 editionCapacity stated as 3.563 MW (not stated in the October 2023 edition)
  • MANOR COURT FARM PVNovember 2023 editionCapacity changed from 4.632 MW to 4.18 MW
  • MARSH FARM B PVNovember 2023 editionCapacity stated as 11.4 MW (not stated in the October 2023 edition)
  • NORRINGTON PV GENERATIONNovember 2023 editionCapacity stated as 9.5 MW (not stated in the October 2023 edition)
  • Site not namedNovember 2023 editionCapacity changed from 7.95 MW to 7.553 MW
  • Site not namedNovember 2023 editionCapacity stated as 7.268 MW (not stated in the October 2023 edition)
  • UNIT 2November 2023 editionCapacity changed from 4.211 MW to 3.849 MW
  • UNIT 2November 2023 editionExport capacity changed from 3.8 MW to 3.849 MW
  • UNIT A1 MARSTON TRADING ESTATENovember 2023 editionCapacity changed from 2.535 MW to 2.408 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.