Capenhurst
Grid supply point in Merseyside, Cheshire and North Wales (SPM)
SPEN Embedded Capacity Register >1MW, September 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Storage | 5 | 374 MW | 20 MW | 354 MW |
| Gas and other fossil | 9 | 188 MW | 165 MW | 23 MW |
| Solar | 4 | 28.4 MW | 20.4 MW | 8 MW |
| Bioenergy and waste | 3 | 9.7 MW | 9.7 MW | – |
| Other or not stated | 1 | 1.6 MW | 1.6 MW | – |
Storage capacity in MWh: not published by SPEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A | 2 | 16.4 MW | – | ||||||||||||||||||||||||||
2 sites, 16.4 MW: 16.4 MW connected
| |||||||||||||||||||||||||||||
| CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A | 3 | 9.7 MW | – | ||||||||||||||||||||||||||
3 sites, 9.7 MW: 9.7 MW connected
| |||||||||||||||||||||||||||||
| CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A | 1 | 2 MW | – | ||||||||||||||||||||||||||
1 site, 2 MW: 2 MW connected
| |||||||||||||||||||||||||||||
| CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A | 1 | 1.6 MW | – | ||||||||||||||||||||||||||
1 site, 1.6 MW: 1.6 MW connected
| |||||||||||||||||||||||||||||
| CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A | 1 | 1 MW | – | ||||||||||||||||||||||||||
1 site, 1 MW: 1 MW connected
| |||||||||||||||||||||||||||||
| CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A | 4 | 14.9 MW | 83 MW | ||||||||||||||||||||||||||
4 sites, 97.9 MW: 14.9 MW connected, 83 MW accepted to connect
| |||||||||||||||||||||||||||||
| BRIDGEWATER PAPER | 1 | 90 MW | – | ||||||||||||||||||||||||||
1 site, 90 MW: 90 MW connected
| |||||||||||||||||||||||||||||
| HOOTON PARK 1B / HOOTON PARK 2B | 3 | 34.7 MW | 22.5 MW | ||||||||||||||||||||||||||
3 sites, 57.2 MW: 34.7 MW connected, 22.5 MW accepted to connect
| |||||||||||||||||||||||||||||
| BROMBOROUGH GT2 / ELLESMERE PORT GT1 / HOOTON PK GT1A / HOOTON PK GT2A | 1 | 2.5 MW | – | ||||||||||||||||||||||||||
1 site, 2.5 MW: 2.5 MW connected
| |||||||||||||||||||||||||||||
| BROMBOROUGH GT2 / ELLESMERE PORT GT1 / HOOTON PK GT1A / HOOTON PK GT2A | 3 | 44.1 MW | – | ||||||||||||||||||||||||||
3 sites, 44.1 MW: 44.1 MW connected
| |||||||||||||||||||||||||||||
| Not stated | 2 | – | 279 MW | ||||||||||||||||||||||||||
2 sites, 279 MW: 279 MW accepted to connect
| |||||||||||||||||||||||||||||
What changed recently
Changes to sites here found in both editions of each pair, newest first.
August 2026 edition to September 2026 edition: 22 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.
- Gowy Landfill 3June 2026 editionTarget energisation date not stated (1 Dec 2030 in the May 2026 edition)
- Iddenshall GrangeJune 2026 editionIn a connection queue changed from “yes” to “no”
- Iddenshall GrangeJune 2026 editionStatus changed from “accepted to connect” to “connected”
- Bridgewater PaperMay 2026 editionTarget energisation date stated as 30 Sep 2023 (not stated in the April 2026 edition)
- Dock Yard PowerMay 2026 editionCustomer stated as Urban Reserve (Assettco) Ltd (not stated in the April 2026 edition)
- Gowy Landfill 3May 2026 editionTarget energisation date stated as 1 Dec 2030 (not stated in the April 2026 edition)
- Hooton Bio PowerMay 2026 editionCustomer stated as North Lanarkshire Bio Power Limited (not stated in the April 2026 edition)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.