Distribution / SSEN / Grid supply point

LOVEDEAN GSP

Grid supply point in Southern England (SEPD)

SSEN Embedded Capacity Register, September 2026 edition

59sites of 1 MW and over
1.1 GWcapacity
0.3 GWconnected (38 sites)
0.8 GWaccepted to connect (21 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage11679 MW58 MW621 MW
Solar31265 MW171 MW94 MW
Other or not stated9121 MW83 MW38 MW
Bioenergy and waste618.4 MW18.4 MW–
Wind116.2 MW16.2 MW–
Gas and other fossil112.2 MW–12.2 MW

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
FORT WIDLEY138 MW–
FORT WIDLEY2–240 MW
CHICHESTER612.6 MW36.5 MW
CHICHESTER524.2 MW12.2 MW
CHICHESTER112.4 MW–
CHICHESTER19.5 MW–
CHICHESTER19 MW–
CHICHESTER28.6 MW–
CHICHESTER18 MW–
CHICHESTER16.7 MW–
CHICHESTER15.7 MW–
CHICHESTER14.8 MW–
CHICHESTER14.8 MW–
CHICHESTER14 MW–
CHICHESTER1–1.6 MW
CHICHESTER1–70.4 MW
FAREHAM138 MW–
FAREHAM1–24 MW
FAREHAM120 MW–
FAREHAM116.7 MW–
FAREHAM338 MW49.9 MW
HAVANT1–57 MW
HAVANT23.1 MW20 MW
HAVANT13.8 MW–
HAVANT13.3 MW–
HAVANT1–1.2 MW
HUNSTON35.8 MW32 MW
HUNSTON411.4 MW1.8 MW
HUNSTON1–9.8 MW
HUNSTON11.8 MW–
HUNSTON1–0.5 MW
WYMERING116 MW–
WYMERING1–5.1 MW
WYMERING12.4 MW–
WYMERING1–2.2 MW
WYMERING12 MW–
PORTSMOUTH116.2 MW–
Not stated1–100 MW
Not stated220 MW101 MW

Not found in SSEN's September 2026 edition

5 sites last found at this grid supply point were not found in this edition by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

August 2026 edition to September 2026 edition: 59 sites matched. 2 sites at this grid supply point couldn't be matched between the two editions, because their details changed or they appear in only one.

  • BAKERS FARMNovember 2023 editionCapacity changed from 10.526 MW to 9.5 MW
  • BAKERS FARMNovember 2023 editionCustomer changed from SIDLESHAM to SIDLESHAM RENEWABLES LIMITED
  • NEWLANDS FARMNovember 2023 editionCapacity changed from 21.05 MW to 19.998 MW
  • NEWLANDS FARMNovember 2023 editionCapacity changed from 37.895 MW to 16.673 MW
  • NEWLANDS FARMNovember 2023 editionCustomer changed from SUNSAVE 10 (FAREHAM) LTD to SUNSAVE 1DATA NOT AVAILABLE (FAREHAM) LTD
  • Site not namedNovember 2023 editionCapacity changed from 2.118 MW to 2.012 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.