Distribution / SSEN / Grid supply point

LOVEDEAN GSP

Grid supply point in Southern England (SEPD)

SSEN Embedded Capacity Register, November 2026 edition

58sites of 1 MW and over
1.1 GWcapacity
0.3 GWconnected (38 sites)
0.8 GWaccepted to connect (20 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage10678 MW58 MW620 MW
Solar31265 MW171 MW94 MW
Other or not stated9121 MW83 MW38 MW
Bioenergy and waste618.4 MW18.4 MW–
Wind116.2 MW16.2 MW–
Gas and other fossil112.2 MW–12.2 MW

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
FORT WIDLEY138 MW–
FORT WIDLEY2–240 MW
CHICHESTER612.6 MW36.5 MW
CHICHESTER524.2 MW12.2 MW
CHICHESTER112.4 MW–
CHICHESTER19.5 MW–
CHICHESTER19 MW–
CHICHESTER28.6 MW–
CHICHESTER18 MW–
CHICHESTER16.7 MW–
CHICHESTER15.7 MW–
CHICHESTER14.8 MW–
CHICHESTER14.8 MW–
CHICHESTER14 MW–
CHICHESTER1–1.6 MW
CHICHESTER1–70.4 MW
FAREHAM138 MW–
FAREHAM1–24 MW
FAREHAM120 MW–
FAREHAM116.7 MW–
FAREHAM338 MW49.9 MW
HAVANT1–57 MW
HAVANT23.1 MW20 MW
HAVANT13.8 MW–
HAVANT13.3 MW–
HAVANT1–1.2 MW
HUNSTON35.8 MW32 MW
HUNSTON411.4 MW1.8 MW
HUNSTON1–9.8 MW
HUNSTON11.8 MW–
WYMERING116 MW–
WYMERING1–5.1 MW
WYMERING12.4 MW–
WYMERING1–2.2 MW
WYMERING12 MW–
PORTSMOUTH116.2 MW–
Not stated1–100 MW
Not stated220 MW101 MW

Search and filter all 58 sites at LOVEDEAN GSP

Not found among the sites of 1 MW and over in SSEN’s November 2026 edition

2 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

Listed at under 1 MW in SSEN’s November 2026 edition

2 sites last listed here at 1 MW or over are listed in this edition at under 1 MW. QueueWatch keeps their pages for six months.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 58 sites matched. 2 sites at this grid supply point couldn’t be matched between the two editions, because their details changed or they appear in only one.

2 sites without a match in the other edition
In the October 2026 edition only (2)
  • 1MVA + 127.8KW PVSouthern England (SEPD)Accepted to connectListed at under 1 MW in the November 2026 edition0.128 MW
  • Site not namedSouthern England (SEPD)Accepted to connectListed at under 1 MW in the November 2026 edition0.48 MW
  • BINSTEAD FARMNovember 2026 editionExport capacity changed from 4.9 MW to 12.174 MW
  • 100MW BESSOctober 2026 editionExport capacity changed from 100 MW to 105.263 MW
  • BINSTEAD FARMOctober 2026 editionExport capacity changed from 12.174 MW to 4.9 MW
  • Site not namedOctober 2026 editionExport capacity changed from 0 MW to 1.574 MW
  • STAGECOACHOctober 2026 editionExport capacity changed from 3.7 MW to 2.2 MW
  • BINSTEAD FARMAugust 2026 editionExport capacity changed from 4.9 MW to 12.174 MW
  • STAGECOACHAugust 2026 editionExport capacity changed from 2.2 MW to 3.7 MW
  • 100MW BESSJuly 2026 editionExport capacity changed from 105.263 MW to 100 MW
  • BAKER BARRACKS - PVJuly 2026 editionFlexible connection stated as “yes” (not stated in the June 2026 edition)
  • BINSTEAD FARMJuly 2026 editionExport capacity changed from 12.174 MW to 4.9 MW
  • 100MW BESSJune 2026 editionExport capacity changed from 100 MW to 105.263 MW
  • BINSTEAD FARMJune 2026 editionExport capacity changed from 4.9 MW to 12.174 MW
  • 100MW BESSMay 2026 editionExport capacity changed from 105.263 MW to 100 MW
  • BINSTEAD FARMMay 2026 editionCustomer not stated (name not shown in the April 2026 edition)
  • BINSTEAD FARMMay 2026 editionExport capacity changed from 12.174 MW to 4.9 MW
  • STAGECOACHMay 2026 editionExport capacity changed from 3.7 MW to 2.2 MW
  • 100MW BESSApril 2026 editionExport capacity changed from 100 MW to 105.263 MW
  • 100MW BESSFebruary 2026 editionExport capacity changed from 99.9 MW to 100 MW
  • STAGECOACHFebruary 2026 editionExport capacity changed from 0.999 MW to 3.7 MW
  • FAREHAMApril 2025 editionTechnology stated as Storage (not stated in the March 2025 edition)
  • INFINIS LIMITEDApril 2025 editionTechnology stated as Bioenergy and waste (not stated in the March 2025 edition)
  • LOVEDEAN LIMITEDApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
  • NEWLANDS FARMApril 2025 editionTechnology stated as Storage (not stated in the March 2025 edition)
  • Site not namedApril 2025 editionTechnology stated as Bioenergy and waste (not stated in the March 2025 edition)
  • VEOLIA ES (UK) LIMITEDApril 2025 editionTechnology stated as Bioenergy and waste (not stated in the March 2025 edition)
  • 100MW BESSFebruary 2025 editionExport capacity changed from 100 MW to 99.9 MW
  • BAKERS FARMNovember 2023 editionCapacity changed from 10.526 MW to 9.5 MW
  • BAKERS FARMNovember 2023 editionCustomer changed from SIDLESHAM to SIDLESHAM RENEWABLES LIMITED
  • BATLEY'S POWER STATIONNovember 2023 editionFlexible connection not stated (“no” in the October 2023 edition)
  • BATLEY'S POWER STATIONNovember 2023 editionTechnology not stated (Bioenergy and waste in the October 2023 edition)
  • FAREHAMNovember 2023 editionCapacity stated as 38 MW (not stated in the October 2023 edition)
  • FAREHAMNovember 2023 editionCustomer stated as FAREHAM (not stated in the October 2023 edition)
  • FAREHAMNovember 2023 editionFlexible connection not stated (“no” in the October 2023 edition)
  • NEWLANDS FARMNovember 2023 editionCapacity changed from 21.05 MW to 19.998 MW
  • NEWLANDS FARMNovember 2023 editionCustomer stated, name not shown (not stated in the October 2023 edition)
  • NEWLANDS FARMNovember 2023 editionTechnology not stated (Other in the October 2023 edition)
  • NEWLANDS FARMNovember 2023 editionCapacity changed from 37.895 MW to 16.673 MW
  • NEWLANDS FARMNovember 2023 editionCustomer changed from SUNSAVE 10 (FAREHAM) LTD to SUNSAVE 1DATA NOT AVAILABLE (FAREHAM) LTD
  • NEWLANDS FARMNovember 2023 editionExport capacity changed from 34.2 MW to 16.673 MW
  • PEAKGEN HAVANTNovember 2023 editionCustomer not stated (PEAKGEN HAVANT in the October 2023 edition)
  • PEAKGEN HAVANTNovember 2023 editionFlexible connection not stated (“yes” in the October 2023 edition)
  • PEAKGEN HAVANTNovember 2023 editionTechnology changed from Gas and other fossil to Other
  • Site not namedNovember 2023 editionCapacity changed from 2.118 MW to 2.012 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.