QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / SPEN / Grid supply point

Dumfries

Grid supply point in Central and Southern Scotland (SPD)

SPEN Embedded Capacity Register >1MW, September 2026 edition

7sites of 1 MW and over
176 MWcapacity
56 MWconnected (4 sites)
120 MWaccepted to connect (3 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage3120 MW–120 MW
Wind248.2 MW48.2 MW–
Bioenergy and waste27.7 MW7.7 MW–

Storage capacity in MWh: not published by SPEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Not stated118.2 MW–
Not stated27.7 MW–
Not stated430 MW120 MW

Search and filter all 7 sites at Dumfries

Not found among the sites of 1 MW and over in SPEN’s September 2026 edition

3 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

August 2026 edition to September 2026 edition: 7 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.

No change to any detail QueueWatch tracks for these sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.