Distribution / Northern Powergrid / Grid supply point

Norton

Grid supply point in North East (Northern Powergrid)

Northern Powergrid Embedded Capacity Register 1MW and Over, September 2026 edition

67sites of 1 MW and over
2 GWcapacity
0.4 GWconnected (39 sites)
1.6 GWaccepted to connect (28 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar351.2 GW0.2 GW1 GW
Storage6594 MW–594 MW
Bioenergy and waste10129 MW64 MW65 MW
Gas and other fossil1350.4 MW50.4 MW–
Wind330.4 MW30.4 MW–

Storage capacity: 5 sites here state 679 MWh, 679 MWh accepted to connect.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Leeming Bar/Skeeby1–100 MW
Leeming Bar/Skeeby239 MW50 MW
Leeming Bar/Skeeby173.2 MW–
Leeming Bar/Skeeby1–49.5 MW
Leeming Bar/Skeeby1–30 MW
Leeming Bar/Skeeby1–25 MW
Leeming Bar/Skeeby1–22.5 MW
Leeming Bar/Skeeby112.5 MW–
Leeming Bar/Skeeby19.3 MW–
Leeming Bar/Skeeby29 MW–
Leeming Bar/Skeeby25.4 MW–
Leeming Bar/Skeeby15 MW–
Mill Lane2–360 MW
Darlington North1–64.3 MW
Darlington North1–61.9 MW
Darlington North1–40 MW
Darlington North1–39 MW
Darlington North1–35 MW
Darlington North123 MW–
Darlington North112.3 MW–
Darlington North312.1 MW–
Darlington North25.6 MW–
Darlington North12.3 MW–
North Tees2–54.9 MW
North Tees123 MW–
North Tees120.1 MW–
North Tees412.9 MW1.3 MW
North Tees210.8 MW–
North Tees1–10 MW
North Tees110 MW–
North Tees14.9 MW–
North Tees13 MW–
North Tees11.6 MW–
California Farm1–150 MW
Thornley Close Farm1–119 MW
Bowesfield1–50 MW
Bowesfield1–46.2 MW
Bowesfield110.3 MW–
Bowesfield25.8 MW–
Bowesfield13.7 MW–
Darlington Central1–38 MW
Darlington Central37.5 MW23 MW
Darlington Central1–19 MW
Darlington Central13.4 MW–
Norton Back Lane1–89.9 MW
Hell Hole Farm1–80 MW
Ketton Solar1–52 MW
Norton 132/11kV517.4 MW8.6 MW

Not found in Northern Powergrid's September 2026 edition

37 sites last found at this grid supply point were not found in this edition by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

August 2026 edition to September 2026 edition: 60 sites matched. 14 sites at this grid supply point couldn't be matched between the two editions, because their details changed or they appear in only one.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.