Distribution / Northern Powergrid / Grid supply point

Ferrybridge B

Grid supply point in Yorkshire (Northern Powergrid)

Northern Powergrid Embedded Capacity Register 1MW and Over, September 2026 edition

57sites of 1 MW and over
2.4 GWcapacity
0.3 GWconnected (29 sites)
2.1 GWaccepted to connect (28 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage131.6 GW–1.6 GW
Solar24500 MW32 MW468 MW
Bioenergy and waste9213 MW185 MW28 MW
Gas and other fossil9116 MW91 MW25 MW
Wind19.7 MW9.7 MW–
Other or not stated11.2 MW1.2 MW–

Storage capacity: 2 sites here state 40 MWh, 40 MWh accepted to connect.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Bluebell Battery Bank1–240 MW
NEL Conway2 BESS1–240 MW
NEL Springfield1–240 MW
Bramham1–68.4 MW
Bramham1–40 MW
Bramham1–35 MW
Bramham1–25 MW
Bramham1–17.7 MW
Bramham19.7 MW–
Bramham1–9.2 MW
Bramham39.1 MW–
Bramham27 MW–
Bramham11.4 MW–
Bramham11.2 MW–
NEL Hunter1–200 MW
Stocking Lane BESS1–200 MW
Featherstone132 MW–
Featherstone132 MW–
Featherstone1–21.9 MW
Featherstone19.7 MW–
Featherstone28 MW1.5 MW
Featherstone18 MW–
Featherstone14 MW–
Featherstone11.5 MW–
Featherstone11.4 MW–
Fryston Lane282 MW28 MW
Fryston Lane BESS1–100 MW
Ferrybridge BESS1–94.9 MW
Scalm Park1–89.9 MW
Hayton House Farm1–81.9 MW
Elawan Energy BESS Whinmoor1–80 MW
Ferrybridge Multifuel177 MW–
Sunny Dairy Farm Energy Park1–70 MW
Cawood Hybrid1–64 MW
Whinmoor1–50 MW
Whinmoor24.4 MW–
Whinmoor14 MW–
Whinmoor21.8 MW2.1 MW
Whinmoor11.2 MW–
Cooklands Farm1–50 MW
Holmfield Lane BESS1–50 MW
Kirkhaw Lane1–20 MW
Kirkhaw Lane311 MW1.6 MW
Kirkhaw Lane27.9 MW–
Kirkhaw Lane23.5 MW–
Kirkhaw Lane1–1.2 MW

Not found in Northern Powergrid's September 2026 edition

30 sites last found at this grid supply point were not found in this edition by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

August 2026 edition to September 2026 edition: 53 sites matched. 8 sites at this grid supply point couldn't be matched between the two editions, because their details changed or they appear in only one.

  • York Road PVJuly 2026 editionStatus changed from “accepted to connect” to “connected”
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.