Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue.

More analyses are on the way.

Scottish Power Renewables (UK) Limited

Customer named in the TEC register

34projects in the register
5.3 GWstill to connect
0 MWof that with Gate 2 offers
1.6 GWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Arecleoch Extension WindfarmArecleoch 132/33kVOnshore wind72.831 Aug 2026 Past dateNot statedScoping
Whitelee ExtensionWhitelee Extension 275/33kVStorage with solar or wind321 Dec 2026Not statedBuilt
Dersalloch Wind Farm ExtensionDersalloch 132/33kVStorage1131 Oct 2027Not statedScoping
HarestanesHarestanes West Wind Farm 132/33kVStorage with solar or wind38.331 Mar 2028Not statedUnder Construction/Commissioning
Harestanes West Wind FarmHarestanes West Wind Farm 132/33kVOnshore wind811 Sep 2029Not statedScoping
Beinn Tharsuinn RepowerBEINN THURSUNN REPOWER 275/33KVOnshore wind8431 Oct 2029Gate 1Scoping
Carrick Wind FarmCarrick Wind Farm SubstationOnshore wind841 Apr 2030Not statedAwaiting Consents
Hollandmey Renewable Energy DevelopmentHollandmey Renewable Energy Development132/33kV SubstationOnshore wind49.531 May 2030Not statedConsents Approved
Euchanhead Wind FarmEuchanhead 132kV SubstationOnshore wind11229 Oct 2030Not statedAwaiting Consents
Earraghail Renewable Energy Development (formerly Skipness & Corranbuie)Earraghail 275/33KV SubstationStorage with solar or wind1051 Apr 2031Not statedScoping
WhiteleeWhitelee 275/33kVOnshore wind5132 May 2031Not statedScoping
Wether HillWether Hill 132/33KV SubstationOnshore wind6629 Sep 2031Gate 1Scoping
Fasque WindfarmFetteresso 132kV substationOnshore wind10531 Oct 2031Gate 1Scoping
Hare Hill RepoweringHare Hill Repowering 132/33kV SubstationOnshore wind11431 Oct 2031Gate 1Scoping
Dunlaw ExtensionDunlaw Extension 132/33kVOnshore wind1261 Apr 2032Not statedBuilt
Sheirdrim Wind FarmSheirdrim 132kV SubstationOnshore wind841 Apr 2032Gate 1Scoping
ArecleochArecleoch 132/33kVOnshore wind21615 Jun 2032Not statedScoping
BlacklawBlacklaw 132/33kVStorage with solar or wind2228 Oct 2032Not statedScoping
Clauchrie WindfarmClauchrie 132/33KV SubstationStorage with solar or wind10831 May 2033Gate 1Scoping
Machair Offshore Wind FarmMachair 275/66kV Offshore SubstationOffshore wind2,00016 Sep 2033Not statedScoping
Beinn an Tuirc 1Beinn an Tuirc SubstationOnshore wind95.231 Oct 2034Gate 1Scoping
SPR CS1SPR CS1 275/66KV OFFSHORE SUBSTATIONOffshore wind1,00031 Oct 2037Gate 1Scoping
ArdkinglasArdkinglas GSPOnshore wind0ConnectedNot statedBuilt
Beinn an Tuirc 2Carradale 1 GSPOnshore wind0ConnectedNot statedBuilt
Beinn an Tuirc 3Carradale 1 GSPOnshore wind0ConnectedNot statedBuilt
Beinn TharsuinnAlness GSPOnshore wind0ConnectedNot statedBuilt
Blacklaw ExtensionBlacklaw Extension 132/33kVStorage with solar or wind0ConnectedNot statedBuilt
Dersalloch Wind FarmDersalloch 132/33kVOnshore wind0ConnectedNot statedBuilt
Ewe HillEwehill 132/33kVOnshore wind0ConnectedNot statedBuilt
Glen App WindfarmGlen App 33kVOnshore wind0ConnectedNot statedBuilt
Halsary Wind FarmMybster 3 33kV SubstationOnshore wind0ConnectedNot statedBuilt
Hare Hill Extension Wind FarmCoylton 132/33kVOnshore wind0ConnectedNot statedBuilt
Kilgallioch Wind FarmKilgallioch 275kV SubstationOnshore wind0ConnectedNot statedBuilt
Mark Hill Wind FarmMark Hill 275/132kVOnshore wind0ConnectedNot statedBuilt

Recent changes

  • Beinn an Tuirc 1North Scotland, Onshore windMarked as Gate 1
  • Dersalloch Wind Farm ExtensionSouth Scotland, Storage69 MW no longer connected
  • Dersalloch Wind Farm ExtensionSouth Scotland, StorageCapacity changed from 16 MW to 11 MW
  • Dersalloch Wind Farm ExtensionSouth Scotland, StorageStatus changed from Consents Approved to Scoping
  • Dersalloch Wind Farm ExtensionSouth Scotland, StorageTechnology changed from Storage, Onshore wind to Storage
  • Sheirdrim Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Mar 2032 to 1 Apr 2032 (2 days later)
  • Sheirdrim Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2032 to 30 Mar 2032 (2 days earlier)
  • Sheirdrim Wind FarmNorth Scotland, Onshore windMarked as Gate 1
  • Carrick Wind FarmSouth Scotland, Onshore windStatus changed from Scoping to Awaiting Consents
  • Euchanhead Wind FarmSouth Scotland, Onshore windStatus changed from Scoping to Awaiting Consents
  • Kilgallioch Wind FarmSouth Scotland, Onshore windRestructured from 2 stages (228 MW connected, 46 MW connected) to 1 stage (274 MW connected)
  • Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: 46 MW now connectedConnected
  • Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Gate marking removed (was Gate 2)
  • Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Status changed from Consents Approved to Built
  • Kilgallioch Wind FarmSouth Scotland, Onshore windStage 2: Given a Gate 2 connection offerGate 2
  • SPR CS1England and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to SPR CS1 275/66KV OFFSHORE SUBSTATION
  • SPR CS1England and Wales, Offshore windMarked as Gate 1
  • Clauchrie WindfarmSouth Scotland, Storage with solar or windMarked as Gate 1
  • Hare Hill RepoweringSouth Scotland, Onshore windMarked as Gate 1
  • Wether HillSouth Scotland, Onshore windMarked as Gate 1
  • Beinn Tharsuinn RepowerNorth Scotland, Onshore windTransmission owner changed from NGET to SHET
  • Beinn Tharsuinn RepowerNorth Scotland, Onshore windConnection point changed from Beinn Tharsuinn Repower 132/33kV Substation to BEINN THURSUNN REPOWER 275/33KV
  • Beinn Tharsuinn RepowerNorth Scotland, Onshore windTransmission owner changed from SHET to NGET
  • Beinn Tharsuinn RepowerNorth Scotland, Onshore windMarked as Gate 1
  • Clauchrie WindfarmSouth Scotland, Storage with solar or windConnection point changed from Clauchrie 132kV Substation to Clauchrie 132/33KV Substation
  • Fasque WindfarmNorth Scotland, Onshore windMarked as Gate 1
  • Arecleoch Extension WindfarmSouth Scotland, Onshore windRenamed from Arecleoch Windfarm Extension
  • Kilgallioch Wind FarmSouth Scotland, Onshore windRenamed from Kilgallioch Wind Farm and Kilgallioch Wind Farm Extension - Turbines
  • Beinn an Tuirc 1North Scotland, Onshore windConnection point changed from Carradale 1 GSP to Beinn an Tuirc Substation
  • Earraghail Renewable Energy Development (formerly Skipness & Corranbuie)North Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Solar, Onshore wind
  • Clauchrie WindfarmSouth Scotland, Storage with solar or windConnection date moved from 31 Oct 2027 to 31 May 2033 (+67 months)+67 mo
  • Dersalloch Wind FarmSouth Scotland, Onshore windCapacity changed from 11 MW to 0 MW
  • Dersalloch Wind FarmSouth Scotland, Onshore windConnection date removed (was 31 Oct 2027)
  • Dersalloch Wind Farm ExtensionSouth Scotland, StorageAdded to the registerNew
  • HarestanesSouth Scotland, Storage with solar or windConnection point changed from Harestanes 132/33kV to Harestanes West Wind Farm 132/33kV
  • Harestanes West Wind FarmSouth Scotland, Onshore windConnection point changed from Old Forest of Ae 33kV Substation to Harestanes West Wind Farm 132/33kV
  • Whitelee ExtensionSouth Scotland, Storage with solar or windTechnology changed from Storage, Solar, Onshore wind to Storage, Solar, Onshore wind, Hydrogen
  • Euchanhead Wind FarmSouth Scotland, Onshore windConnection date moved from 29 Oct 2029 to 29 Oct 2030 (+12 months)+12 mo
  • Fasque WindfarmNorth Scotland, Onshore windConnection point changed from Fasque Wind Farm 132kV Substation to Fetteresso 132kV substation
  • Fasque WindfarmNorth Scotland, Onshore windCapacity changed from 90 MW to 105 MW
  • Hare Hill RepoweringSouth Scotland, Onshore windConnection date moved from 31 Oct 2029 to 31 Oct 2031 (+24 months)+24 mo
  • Harestanes West Wind FarmSouth Scotland, Onshore windRestructured from 1 stage (56 MW from 31 Oct 2027) to 2 stages (56 MW from 1 Sep 2029, 25 MW from 1 Jul 2035). First connection date +22 months+22 mo
  • Hollandmey Renewable Energy DevelopmentNorth Scotland, Onshore windConnection date moved from 1 May 2029 to 31 May 2030 (+13 months)+13 mo
  • Euchanhead Wind FarmSouth Scotland, Onshore windTechnology changed from Storage, Onshore wind to Onshore wind
  • WhiteleeSouth Scotland, Onshore windStage 1: Technology changed from Storage, Onshore wind to Onshore wind
  • WhiteleeSouth Scotland, Onshore windStage 2: Capacity changed from 355 MW to 50 MW
  • WhiteleeSouth Scotland, Onshore windStage 2: Connection date moved from 15 Jun 2029 to 2 May 2031 (+23 months)+23 mo
  • WhiteleeSouth Scotland, Onshore windStage 2: Technology changed from Storage, Onshore wind to Onshore wind
  • WhiteleeSouth Scotland, Onshore windNew stage added (305 MW from 25 Apr 2033)
  • WhiteleeSouth Scotland, Onshore windNew stage added (158 MW from 27 Apr 2034)
  • Harestanes West Wind FarmSouth Scotland, Onshore windRenamed from Old Forest of Ae
  • Earraghail Renewable Energy Development (formerly Skipness & Corranbuie)North Scotland, Storage with solar or windTechnology changed from Storage, Solar, Onshore wind to Onshore wind
  • Earraghail Renewable Energy Development (formerly Skipness & Corranbuie)North Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Solar, Onshore wind
  • Hollandmey Renewable Energy DevelopmentNorth Scotland, Onshore windStatus changed from Scoping to Consents Approved
  • Whitelee ExtensionSouth Scotland, Storage with solar or windConnection date moved from 31 Mar 2023 to 1 Dec 2026 (+44 months)+44 mo
  • BlacklawSouth Scotland, Storage with solar or windStage 1: Technology changed from Onshore wind to Storage, Onshore wind
  • BlacklawSouth Scotland, Storage with solar or windStage 2: Connection date moved from 15 Jun 2029 to 8 Oct 2032 (+40 months)+40 mo
  • BlacklawSouth Scotland, Storage with solar or windStage 2: Technology changed from Onshore wind to Storage, Onshore wind
  • Blacklaw ExtensionSouth Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
  • Carrick Wind FarmSouth Scotland, Onshore windConnection date moved from 28 Feb 2029 to 1 Apr 2030 (+13 months)+13 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO