PORT 9.75MW PV
ETHICAL POWER CONNECTIONS at LOVEDEAN GSP
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Dec 2027
- Status
- Accepted to connect
- Customer
- ETHICAL POWER CONNECTIONS
- Site name
- PORT 9.75MW PV
- Address
- FERRY FARM 3 NORTH, FERRY FARM SELSEY, CHICHESTER, WEST SUSSEX, PO20 9DR
- Grid reference
- Easting 485027, northing 94693
- Licence area
- Southern England (SEPD)
- Grid supply point
- LOVEDEAN GSP
- Bulk supply point
- HUNSTON
- Primary substation
- SELSEY
- Connection voltage
- 11 kV
- Technology group
- Solar
- Energy source 1
- SOLAR, PHOTOVOLTAIC: 9.75 MW registered
- Registered capacity
- 9.75 MW
- Change to maximum export capacity
- 9.75 MW
- Change to maximum import capacity
- 0.105 MW
- Flexible connection
- Yes
- In a connection queue
- Not published by SSEN
- Date accepted
- 23 Dec 2021
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- August 2023 edition
Change history
Tracked since the August 2023 edition, across 40 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2025 editionTarget energisation date stated as 31 Dec 2027 (not stated in the October 2025 edition)
Also at LOVEDEAN GSP
GSP view57 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.1 GW: 0.3 GW connected, 0.8 GW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?