QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

LAND AT MANOR FARM 3

Name not shown at LOVEDEAN GSP

SSEN Embedded Capacity Register, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
30 Oct 2037
Status
Accepted to connect
Customer
Name not shown
Site name
LAND AT MANOR FARM 3
Address
LAND AT MANOR FARM 3, SHRIPNEY, BOGNOR REGIS, WEST SUSSEX, PO22 9UP
Grid reference
Easting 493499, northing 102153
Licence area
Southern England (SEPD)
Grid supply point
LOVEDEAN GSP
Bulk supply point
CHICHESTER
Primary substation
CHICHESTER
Connection voltage
33 kV
Technology group
Other or not stated
Energy source 1
OTHER, OTHER: 18 MW registered
Registered capacity
18 MW
Change to maximum export capacity
5 MW
Change to maximum import capacity
18.032 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
24 Nov 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
December 2023 edition

Change history

Tracked since the December 2023 edition, across 35 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 30 Oct 2037 (not stated in the October 2025 edition)

Also at LOVEDEAN GSP

GSP view

59 other sites at this grid supply point in the October 2026 edition, 5 of them at CHICHESTER, the same primary substation. In all, the sites here total 1.1 GW: 0.3 GW connected, 0.8 GW accepted to connect.

See all 59

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose